Case 2

Navigation

Good Practices

Fitting

Design

pic16
Figure 1
  • A seal joint (Figure 1) should be provided to prevent moisture penetration through wall adjacent to the bathtub [1-2].
bathtub
Figure 2a
bath_leak01
Figure 2b
  • In addition, it is recommended to fix the bathtub away from wall to minimize chances of water seepage [3] (Figures 2a, 2b).

Construction

apply_sealant
Figure 3
  • Sealant should be applied correctly along the tub in order to obtain impervious joints along the wall joint. The gun should be hold at 450 angle and press the tube uniformly while dragging the tube along the joint in constant speed (Figure 3).

Quality Control

  • Size of the bath is another important parameter to be considered to minimize water splash over the floor to keep the floor dry, so as to minimize the maintenance [4-5] (see Table 1 in BS 6465). In this case, it is a good practice to enclose the bath area.
  • Examine the fitting for damage and ensure satisfactory operation of the fittings prior to use.

Waterproofing

Design

The waterproofing details of bath area are as follows[3, 6-8]:

joint_recommend
Figure 4
  • At the wall joint – minimum upstand 300mm (Figure 4)
bath_leak02
Figure 5
  • At walls – up to 1800mm high within a horizontal radius of 1500mm from a shower rose (Figure 5)
bath_leak03
Figure 6
  • Where a bathtubs are designed only for bathing, upstand of the membrane can be limited to 1500mm above from shower outlet (Figure 6).

Material

  • Select appropriate waterproofing system. Due to wet area’s inherent nature of being small with many penetrations, protrusions and discontinuities, a flexible system is more suitable for internal wet areas.
  • In general, the selected waterproofing material should possess the following qualities:
    • Suitable to its micro-environment conditions such as ventilation and surface dampness (Table 1)
    • Compatible with the other subcomponents such as screed, tile bedding or even type of tiles (in a vertical surface) (Table 1)
    • Easy to apply, especially at pipe penetration areas
    • Be elastic and able to bridge over cold joints and differing materials
    • Have good adhesion and cohesion strengths
    • Able to retain its adhesion and remain stable under extreme fluctuations of temperature
    • Able to resist mechanical damage such as peeling, cracking and rupture prior to screed finish
    • Fully bonded to the substrate so that any leakage may be localised

Check the performance of waterproofing membranes before selecting a suitable system.

ConditionsJustification
1. VentilationAdequate ventilation is necessary for some systems to be cured adequately.

 

  • Rubber-based systems – moderate
  • Acrylic-based systems – moderate
  • Polyurethane systems – very important
  • Cementitious systems – not important
2. Surface finish (vertical)System should be able to accommodate (wall) finishes

 

  • Rubber-based systems – both stone and ceramic tiles are suitable
  • Acrylic-based systems – both stone and ceramic tiles are suitable
  • Polyurethane systems – both stone and ceramic tiles are suitable
  • Cementitious systems – only ceramic tiles are suitable
3. Surface dampness
  • Rubber-based systems – moderate bonding under damp conditions
  • Acrylic-based systems – good bonding under damp conditions
  • Polyurethane systems – good bonding under damp conditions
  • Cementitious systems – very good bonding under damp conditions

Therefore, in general, solvent-based systems are not suitable while water-based systems are suitable for damp surface conditions.

4. Construction timeSystems that require long curing time is not suitable for limited construction time

 

  • Rubber-based systems – Short curing time- 1 hr and 72 hrs before flood test
  • Acrylic-based systems – Long curing time- for total system and 48 hrs before flood test
  • Polyurethane systems – Long curing time- 24 hrs and 72 hrs before flood test
  • Cementitious systems – Short curing time- 1 to 2 hrs and Flood test within 24 hrs

Table 1: Characteristics of a waterproofing system

  • Waterproofing systems selected for use are required to be specified to relevant local building requirements or to International performance standards. These may include subjecting the materials to stringent tests to determine their performance under actual site conditions.

Construction

The waterproofing membrane should be laid appropriately to ensure the watertightness of the system.

The surface should be cleaned or repaired by removing surface contamination or defect to provide excellent bonding property between the substrate surface and membrane (SS CP 82).

Flowing application should be followed up to obtain monolithic structure at the floor trap [6-7].

fillet2
Figure 7
fg_mesh2
Figure 8

Care must be taken to ensure required coverage around floor traps (Figure 7). Brush application of membrane is more suitable at floor trap to ensure good coverage (Figure 8)

Before application process begins, the substrate receiving the waterproofing membrane should be checked and prepared for better bonding as follows:

Quality Control

  • Substrates should be inspected and prepared in accordance to the manufacturer’s recommendations prior to the execution of the waterproofing system.
  • Waterproofing products should be sealed and delivered in original packaging. All materials should be protected from the weather and stored in a dry and secure place.
  • Greater supervision during construction and a skilled labour force are important so as to control and improve the workmanship quality of a product.
  • Checklists for the inspection of waterproofing work can be used as means to inspect the onsite workmanship quality. A continual check should be made on the amount of material that has been used and the area covered to ensure that the recommended coverage rate is being achieved.
  • The membrane should be tested for water-tightness after completion of the application. Make sure the membrane has cured properly before carrying on the test (Table 2).
SystemTime
Rubber-based systems1-72 hrs
Acrylic-based systems48 hrs for total system
Polyurethane systems24-72 hrs
Cementitious systems1-2 hrs and flood test within 24 hrs

Table 2: Curing Time