Wet Area
Construction / Installation
Grading for construction of slope in floor
Factors | Grading criteria | Grade |
Slab casting |
|
Yes: 5 No: 1 |
Embedding of services | The pipes to be embedded in the screed should be checked for proper layout and jointing, else it affects durability of wet area. | Yes: 5 No: 1 |
Laying the slope |
|
Yes: 5 No: 1 |
Grading for installation of waterproofing
Factors | Grading criteria | Grade |
Substrate condition |
|
Yes: 5 No: 1 |
Quality of material |
|
Yes: 5 No: 1 |
Application |
|
Yes: 5 No: 1 |
Inspection and testing |
|
Yes: 5 No: 1 |
Protection | Once installed the membrane should be protected from damage due to foot traffic and cordoned off with an appropriate notice. | Yes: 5 No: 1 |
Grading for installation of finishes (tiles)
Factor | Grading criteria | Grade |
Tiled surface | ||
Base : screed & substrate |
|
Yes: 5 No: 1 |
Preparation of tiles |
|
Yes: 5 No: 1 |
Tiling |
|
Yes: 5 No: 1 |
Grouting |
|
Yes: 5 No: 1 |
Inspection & checking | Checked as per the guideline of CONQUAS 21:
|
Yes: 5 No: 1 |
Protection |
|
Yes: 5 No: 1 |
Painted surface (walls) | ||
Substrate preparation |
|
Yes: 5 No: 1 |
Material quality |
|
Yes: 5 No: 1 |
Application |
|
Yes: 5 No: 1 |
Grading for construction of fixture and fittings
Factor | Grading criteria | Grade |
Installation | Installed as per manufacturer’s instruction or as specified by codes.
|
5 |
Violation of codes or careless installation. E.g. seepage at the junction of discharge pipe and gully pipe through the porous infill if either of the pipes are wrongly installed or ‘short’ and thus leaving a gap at the junction. | 1 |